Opening August 2025

Legacy High School
251,270 sq. ft., 2000 student stations, Administration building, 61 classroom spaces, 20 labs, state-of-the art 750 seat Auditorium and Theater, 1332 seat Gymnasium, new sports fields and an 858 seat Cafeteria. CTE programs to include: Biomedical, Nursing, Dental, Physical Therapy, Hospital, Logistics, Digital Design Video/Cinema Production, Theater, Music, 2D and 3D arts.  Funded by: Bond, Impact Fees, COPs
Tradition DDD

Key milestones achieved

Building 1:
  • Interior rough-in and electrical rough-in are 100% complete.
  • Drywall is complete on the first floor and will be 100% on the second floor by the holidays.
  • Electrical, mechanical, and communication rooms are finished and painted. Cable pulling and rack building are underway.
  • Permanent power setup is progressing, with secondary pulls to the FPL transformer starting 01/13/2025.
  • All air handling units are installed, piped into the chilled water system on the first floor, and work on the second floor is ongoing.
Building 2:
  • Interior CMU, framing, and rough-in are 100% complete.
  • Communication and electrical rooms are finished and painted. Cable pulling and rack building are underway.
  • Gymnasium ductwork is 100% complete, with painting scheduled for next month.
  • All air handling units are installed.
Building 3:
  • Windows are 100% installed; awaiting storefront delivery.
  • Auditorium slab is complete, with interior framing and high-ceiling rough-in beginning 01/13/2025.
  • Music rooms, labs, and Area A are 100% rough-in complete, and drywall installation is ongoing.
Buildings 4 & 5:
  • Structure and roof are complete.
  • Central Energy Plant (CEP) is 95% complete with piping, supports, and pump installations. Chillers are installed, with startup and flushing planned for February 2025.

Sitework:
  • FPL installed all permanent power switch sites and transformers. Temporary power stations passed inspection.
  • Aluminum canopies installation began and will continue into February 2025.
  • Gas utility plans are approved, awaiting Florida City Gas to begin on-site work.
  • Rough grading is progressing and will be completed by the end of January 2025.

Untitled-4
Progress
Plans

Opening January 2026

New Ft. Pierce Westwood
251,270 sq. ft., 2000 student stations, Administration building, 61 classroom spaces, 20 labs, state-of-the art 750 seat Auditorium and Theater, 1332 seat Gymnasium, new sports fields and an 858 seat Cafeteria. CTE programs to include: Biomedical, Nursing, Dental, Physical Therapy, Hospital, Logistics, Digital Design Video/Cinema Production, Theater, Music, 2D and 3D arts.  Funded by: Bond, Impact Fees, COPs
New Fort Pierce Westwood

Key milestones achieved

Key Milestones Achieved
  • Tilt-Up Concrete Wall Panels: All panels were stood and topped out as of January 6, marking a major project milestone.
  • Structural Steel: Installation in Building 1 is complete and progressing well in Building 2.
Building Updates
  • Building 1:
    • 2nd-floor slab on-deck poured in Areas A and C.
    • Roofing, spray fireproofing, MEP (Mechanical, Electrical, Plumbing) rough installation, and framing activities underway in Area C.
  • Building 4:
    • Foundation work is complete.
    • MEP trades are finalizing underground installations.
  • Building 5:
    • Interior framing and MEP rough installations are ongoing.
  • Building 6:
    • Foundation work is scheduled to begin mid-January.
Infrastructure Progress
  • Permanent Power:
    • All materials, excluding transformers, have been delivered by FPL.
    • Installation of permanent power infrastructure is in progress.
  • Water Systems:
    • Water samples passed at two offsite connection points.
    • CORE|Remnant is finalizing connections to the underground water loop.
Athletic Fields
  • Baseball and Softball Fields:
    • Sod has been installed.
    • Fencing materials are being delivered.
    • Dugout coordination is nearing completion.

Sitework
  • Grading and light pole infrastructure work is ongoing at the front entrance, east parking lot, and north parking lot.
Procurement Progress
  • Executed Subcontracts:
    • Advanced Painting (paint), Trident (wood flooring), Daniels Fence (baseball and softball fencing).
  • Pending Subcontracts:
    • Johnson-Lancaster (food service equipment) and Steiner Atlantic (laundry equipment) are being finalized.
  • Upcoming Procurement Packages:
    • Fencing, commercial appliances, flooring, outdoor athletic equipment, general specialties, lockers, and signage.

Next Steps and Focus Areas

  • Begin foundation work on Building 6.
  • Resolve deficiencies with multipurpose fields to meet SLPS standards.
  • Finalize remaining subcontracts and procurement packages.
  • Continue monitoring infrastructure progress and site readiness.