Opening August 2025
Legacy High School
251,270 sq. ft., 2000 student stations, Administration building, 61 classroom spaces, 20 labs, state-of-the art 750 seat Auditorium and Theater, 1332 seat Gymnasium, new sports fields and an 858 seat Cafeteria. CTE programs to include: Biomedical, Nursing, Dental, Physical Therapy, Hospital, Logistics, Digital Design Video/Cinema Production, Theater, Music, 2D and 3D arts. Funded by: Bond, Impact Fees, COPs
Key milestones achieved
Building 1:
- Interior rough-in and electrical rough-in are 100% complete.
- Drywall is complete on the first floor and will be 100% on the second floor by the holidays.
- Electrical, mechanical, and communication rooms are finished and painted. Cable pulling and rack building are underway.
- Permanent power setup is progressing, with secondary pulls to the FPL transformer starting 01/13/2025.
- All air handling units are installed, piped into the chilled water system on the first floor, and work on the second floor is ongoing.
Building 2:
- Interior CMU, framing, and rough-in are 100% complete.
- Communication and electrical rooms are finished and painted. Cable pulling and rack building are underway.
- Gymnasium ductwork is 100% complete, with painting scheduled for next month.
- All air handling units are installed.
Building 3:
- Windows are 100% installed; awaiting storefront delivery.
- Auditorium slab is complete, with interior framing and high-ceiling rough-in beginning 01/13/2025.
- Music rooms, labs, and Area A are 100% rough-in complete, and drywall installation is ongoing.
Buildings 4 & 5:
- Structure and roof are complete.
- Central Energy Plant (CEP) is 95% complete with piping, supports, and pump installations. Chillers are installed, with startup and flushing planned for February 2025.
Sitework:
- FPL installed all permanent power switch sites and transformers. Temporary power stations passed inspection.
- Aluminum canopies installation began and will continue into February 2025.
- Gas utility plans are approved, awaiting Florida City Gas to begin on-site work.
- Rough grading is progressing and will be completed by the end of January 2025.
Progress
Plans
Opening January 2026
New Ft. Pierce Westwood
251,270 sq. ft., 2000 student stations, Administration building, 61 classroom spaces, 20 labs, state-of-the art 750 seat Auditorium and Theater, 1332 seat Gymnasium, new sports fields and an 858 seat Cafeteria. CTE programs to include: Biomedical, Nursing, Dental, Physical Therapy, Hospital, Logistics, Digital Design Video/Cinema Production, Theater, Music, 2D and 3D arts. Funded by: Bond, Impact Fees, COPs
Key milestones achieved
Key Milestones Achieved
- Tilt-Up Concrete Wall Panels: All panels were stood and topped out as of January 6, marking a major project milestone.
- Structural Steel: Installation in Building 1 is complete and progressing well in Building 2.
Building Updates
- Building 1:
- 2nd-floor slab on-deck poured in Areas A and C.
- Roofing, spray fireproofing, MEP (Mechanical, Electrical, Plumbing) rough installation, and framing activities underway in Area C.
- Building 4:
- Foundation work is complete.
- MEP trades are finalizing underground installations.
- Building 5:
- Interior framing and MEP rough installations are ongoing.
- Building 6:
- Foundation work is scheduled to begin mid-January.
Infrastructure Progress
- Permanent Power:
- All materials, excluding transformers, have been delivered by FPL.
- Installation of permanent power infrastructure is in progress.
- Water Systems:
- Water samples passed at two offsite connection points.
- CORE|Remnant is finalizing connections to the underground water loop.
Athletic Fields
-
Baseball and Softball Fields:
- Sod has been installed.
- Fencing materials are being delivered.
- Dugout coordination is nearing completion.
Sitework
- Grading and light pole infrastructure work is ongoing at the front entrance, east parking lot, and north parking lot.
Procurement Progress
- Executed Subcontracts:
- Advanced Painting (paint), Trident (wood flooring), Daniels Fence (baseball and softball fencing).
- Pending Subcontracts:
- Johnson-Lancaster (food service equipment) and Steiner Atlantic (laundry equipment) are being finalized.
- Upcoming Procurement Packages:
- Fencing, commercial appliances, flooring, outdoor athletic equipment, general specialties, lockers, and signage.
Next Steps and Focus Areas
- Begin foundation work on Building 6.
- Resolve deficiencies with multipurpose fields to meet SLPS standards.
- Finalize remaining subcontracts and procurement packages.
- Continue monitoring infrastructure progress and site readiness.